Contract Bid Abstract

SP 001-606-021 - Bituminous Mill and Overlay CSAH 6Anderson Brothers Construction Company of Brainerd LLC Knife River Central Specialities Inc 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$12,500.00$12,500.00$72,500.00$72,500.00$79,000.00$79,000.00
2051.501MAINT & RESTORATION OF HAUL ROADSLS1$1.00$1.00$1.00$1.00$1.00$1.00
2101.501CLEARING & GRUBBINGLS1$21,000.00$21,000.00$50,000.00$50,000.00$125,000.00$125,000.00
2104.502SALVAGE SIGNEACH33$32.00$1,056.00$30.00$990.00$30.00$990.00
2104.502SALVAGE PIPE APRONEACH2$525.00$1,050.00$200.00$400.00$250.00$500.00
2104.503REMOVE PIPE CULVERTSL F54$37.50$2,025.00$14.00$756.00$16.00$864.00
2105.507COMMON EXCAVATION (P)C Y3,228$9.25$29,859.00$8.90$28,729.20$8.00$25,824.00
2105.507GRANULAR BORROW (EV)C Y4,391$10.50$46,105.50$16.45$72,231.95$20.00$87,820.00
2105.603SHOULDER EXCAVATIONL F48,193$0.21$10,120.53$0.40$19,277.20$0.20$9,638.60
2118.507AGGREGATE SURFACING (LV), CLASS SPECIALC Y1,326$28.00$37,128.00$20.00$26,520.00$23.50$31,161.00
2211.507AGGREGATE BASE (LV) CLASS 5C Y1,846$15.75$29,074.50$23.50$43,381.00$22.00$40,612.00
2232.504MILL BITUMINOUS SURFACE (1.5")S Y1,115$4.25$4,738.75$4.00$4,460.00$5.00$5,575.00
2232.504MILL BITUMINOUS SURFACE (2.0")S Y82,085$0.74$60,742.90$1.00$82,085.00$1.25$102,606.25
2357.506BITUMINOUS MATERIAL FOR TACK COATGAL11,365$1.85$21,025.25$0.01$113.65$2.00$22,730.00
2360.509TYPE SP 9.5 WEARING COURSE MIX (2,B)TON13,701$43.25$592,568.25$44.25$606,269.25$49.61$679,706.61
2501.50215" GS PIPE APRONEACH2$500.00$1,000.00$4.95$9.90$300.00$600.00
2501.502INSTALL PIPE APRONEACH2$800.00$1,600.00$345.00$690.00$250.00$500.00
2501.50324" CS PIPE CULVERTL F18$105.00$1,890.00$78.00$1,404.00$35.00$630.00
2501.50324" RC PIPE CULVERTL F12$132.00$1,584.00$84.00$1,008.00$185.00$2,220.00
2501.50315" CS PIPE CULVERTL F76$52.00$3,952.00$58.00$4,408.00$30.00$2,280.00
2540.602MAIL BOX SUPPORTEACH27$100.00$2,700.00$120.00$3,240.00$120.00$3,240.00
2563.601TRAFFIC CONTROLLS1$4,500.00$4,500.00$8,500.00$8,500.00$2,400.00$2,400.00
2564.502INSTALL SIGN TYPE CEACH31$125.00$3,875.00$120.00$3,720.00$120.00$3,720.00
2573.503SILT FENCE, TYPE HIL F665$2.65$1,762.25$2.50$1,662.50$2.50$1,662.50
2574.507COMMON TOPSOIL BORROWC Y200$30.00$6,000.00$30.00$6,000.00$45.00$9,000.00
2574.508FERTILIZER TYPE 3LB1,880$0.73$1,372.40$0.69$1,297.20$0.69$1,297.20
2575.504EROSION CONTROL BLANKETS CATEGORY 3NS Y1,689$1.85$3,124.65$1.75$2,955.75$1.75$2,955.75
2575.505RAPID STABILIZATION METHOD 2ACRE2.7$475.00$1,282.50$450.00$1,215.00$450.00$1,215.00
2575.505SEEDING (P)ACRE9.4$210.00$1,974.00$200.00$1,880.00$200.00$1,880.00
2575.508SEED MIXTURE 25-141LB555$3.45$1,914.75$3.25$1,803.75$3.25$1,803.75
2575.508HYDRAULIC BONDED FIBER MATRIXLB32,900$1.32$43,428.00$1.25$41,125.00$1.25$41,125.00
2580.503INTERIM PAVEMENT MARKINGL F84,336$0.19$16,023.84$0.18$15,180.48$0.11$9,276.96
2582.5036" SOLID LINE MULTI COMPL F26,408$0.38$10,035.04$0.36$9,506.88$0.36$9,506.88
2582.5036" SOLID LINE MULTI COMP GR IN (WR)L F53,862$0.85$45,782.70$0.81$43,628.22$0.80$43,089.60
2582.6036" BROKEN LINE MULTI COMPL F3,405$0.38$1,293.90$0.36$1,225.80$0.36$1,225.80
 Totals for project SP 001-606-021 $1,024,089.71 $1,158,174.73 $1,351,656.90
 
SAP 001-632-007 - Agg Base/Shoulder, Bit Surfacing/StripingAnderson Brothers Construction Company of Brainerd LLC Knife River Central Specialities Inc 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$8,400.00$8,400.00$32,000.00$32,000.00$50,000.00$50,000.00
2051.501MAINT & RESTORATION OF HAUL ROADSLS1$1.00$1.00$1.00$1.00$1.00$1.00
2102.503PAVEMENT MARKING REMOVALL F1,197$1.00$1,197.00$1.00$1,197.00$1.00$1,197.00
2104.502SALVAGE SIGNEACH4$32.00$128.00$30.00$120.00$30.00$120.00
2104.503SAWING BIT PAVEMENT (FULL DEPTH)L F728$2.00$1,456.00$1.75$1,274.00$3.00$2,184.00
2104.504REMOVE BITUMINOUS PAVEMENTS Y217$3.00$651.00$9.00$1,953.00$15.00$3,255.00
2105.507COMMON EXCAVATION (P)C Y322$8.50$2,737.00$15.00$4,830.00$10.00$3,220.00
2118.509AGGREGATE SURFACING CLASS 1TON4,059$16.50$66,973.50$14.30$58,043.70$15.00$60,885.00
2211.509AGGREGATE BASE CLASS 5TON10,339$9.20$95,118.80$10.60$109,593.40$12.00$124,068.00
2211.607SALVAGE AGGREGATE (EV)C Y753$5.00$3,765.00$11.60$8,734.80$35.00$26,355.00
2232.504MILL BITUMINOUS SURFACE (2.0")S Y220$4.50$990.00$6.00$1,320.00$5.00$1,100.00
2357.506BITUMINOUS MATERIAL FOR TACK COATGAL2,705$1.85$5,004.25$0.01$27.05$2.00$5,410.00
2360.509TYPE SP 9.5 WEARING COURSE MIX (2,B) SPECTON12,038$46.50$559,767.00$45.60$548,932.80$47.48$571,564.24
2540.602RELOCATE MAIL BOX SUPPORTEACH19$100.00$1,900.00$130.00$2,470.00$130.00$2,470.00
2563.601TRAFFIC CONTROLLS1$2,000.00$2,000.00$6,000.00$6,000.00$1,600.00$1,600.00
2564.502INSTALL SIGN TYPE CEACH4$135.00$540.00$130.00$520.00$130.00$520.00
2564.518SIGN PANELS TYPE CS F48$52.50$2,520.00$50.00$2,400.00$50.00$2,400.00
2574.508FERTILIZER TYPE 3LB840$0.73$613.20$0.69$579.60$0.69$579.60
2574.607SALVAGED TOPSOIL FROM STOCKPILE (EV)CY808$22.50$18,180.00$18.50$14,948.00$25.50$20,604.00
2575.505SEEDING (P)ACRE2.4$370.00$888.00$350.00$840.00$350.00$840.00
2575.505DISK ANCHORINGACRE2.4$370.00$888.00$350.00$840.00$350.00$840.00
2575.508SEED MIXTURE 25-141LB142$4.17$592.14$3.95$560.90$3.95$560.90
2575.509MULCH MATERIAL TYPE 3TON4.8$285.00$1,368.00$270.00$1,296.00$270.00$1,296.00
2580.503INTERIM PAVEMENT MARKINGL F26,738$0.19$5,080.22$0.18$4,812.84$0.11$2,941.18
2582.5034" SOLID LINE MULTI COMPL F45,660$0.27$12,328.20$0.26$11,871.60$0.24$10,958.40
2582.5034" BROKEN LINE MULTI COMPL F2,989$0.27$807.03$0.26$777.14$0.24$717.36
2582.5036" SOLID LINE MULTI COMP GR IN (WR)L F445$0.85$378.25$0.81$360.45$0.80$356.00
 Totals for project SAP 001-632-007 $794,271.59 $816,303.28 $896,042.68
 
SAP 001-608-006 - Bituminous Mill and OverlayAnderson Brothers Construction Company of Brainerd LLC Knife River Central Specialities Inc 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$11,000.00$11,000.00$32,000.00$32,000.00$25,000.00$25,000.00
2051.501MAINT & RESTORATION OF HAUL ROADSLS1$1.00$1.00$1.00$1.00$1.00$1.00
2104.504REMOVE BITUMINOUS PAVEMENTS Y2,010$1.30$2,613.00$3.20$6,432.00$6.00$12,060.00
2104.504REMOVE CONCRETE PAVEMENTS Y43$10.00$430.00$15.00$645.00$45.00$1,935.00
2105.507SUBGRADE EXCAVATIONC Y112$26.00$2,912.00$20.50$2,296.00$50.00$5,600.00
2118.507AGGREGATE SURFACING (LV), CLASS SPECIALC Y52$32.00$1,664.00$50.00$2,600.00$75.00$3,900.00
2232.504MILL BITUMINOUS SURFACE (1.5")S Y17,673$1.35$23,858.55$1.25$22,091.25$1.85$32,695.05
2357.506BITUMINOUS MATERIAL FOR TACK COATGAL1,882$1.85$3,481.70$0.01$18.82$2.00$3,764.00
2360.509TYPE SP 9.5 WEARING COURSE MIX (2,B)TON2,266$46.00$104,236.00$50.00$113,300.00$61.67$139,744.22
2504.602ADJUST VALVE BOXEACH7$130.00$910.00$750.00$5,250.00$175.00$1,225.00
2506.502CONST DRAINAGE STRUCTURE DESIGN SPECIALEACH1$9,000.00$9,000.00$8,600.00$8,600.00$8,600.00$8,600.00
2521.5184" CONCRETE WALKS F145$25.50$3,697.50$24.00$3,480.00$24.00$3,480.00
2531.503CONCRETE CURB & GUTTER DESIGN B618L F25$75.00$1,875.00$70.00$1,750.00$70.00$1,750.00
2531.6048" CONCRETE VALLEY GUTTERS Y12$220.00$2,640.00$205.00$2,460.00$205.00$2,460.00
2531.618TRUNCATED DOMESS F15$65.00$975.00$60.00$900.00$60.00$900.00
2540.602MAIL BOX SUPPORTEACH2$100.00$200.00$120.00$240.00$120.00$240.00
2563.601TRAFFIC CONTROLLS1$2,500.00$2,500.00$3,500.00$3,500.00$1,600.00$1,600.00
2573.510SEDIMENT REMOVAL VAC TRUCKHOUR10$265.00$2,650.00$225.00$2,250.00$250.00$2,500.00
2575.501TURF ESTABLISHMENTLS1$2,650.00$2,650.00$2,500.00$2,500.00$2,500.00$2,500.00
2580.503INTERIM PAVEMENT MARKINGL F6,154$0.19$1,169.26$0.50$3,077.00$0.11$676.94
2582.5034" SOLID LINE MULTI COMPL F11,822$0.27$3,191.94$0.26$3,073.72$0.24$2,837.28
2582.5034" BROKEN LINE MULTI COMPL F773$0.27$208.71$0.26$200.98$0.24$185.52
2582.50324" SOLID LINE MULTI COMPL F106$8.44$894.64$8.00$848.00$10.00$1,060.00
2582.518PAVT MSSG MULTI COMPS F220$8.44$1,856.80$8.00$1,760.00$9.84$2,164.80
2582.518CROSSWALK MULTI COMPS F420$5.28$2,217.60$5.00$2,100.00$7.66$3,217.20
 Totals for project SAP 001-608-006 $186,832.70 $221,373.77 $260,096.01
 
Contract Total:$2,005,194.00$2,195,851.78$2,507,795.59